For those who are interested in developing power plants in Jakarta Capital City
Special Region, I would like to share the following points with regard to the
above subject. Hoping that they would be of use. Warm regards.
Electricity Condition
Demand for electricity in Jakarta Capital City
Special Region is mainly supplied by Java-Bali interconnection system through
Extra High Voltage Air Channel (500 kV) and High Voltage Air Channel (150 kV and
70 kV) networks. Besides that, it is also supplied by some local Steam Power
Plants, Gas Power Plants, Steam and Gas Power Plants, and some Diesel Power
Plants. Peak utilization in 2011 reached 4,386.71 MW.
Total installed
capacity of power plants in Jakarta Capital City Special Region up to 2011 was
3,009.66 MW consisting of Steam Power Plants 500.00 MW, Gas Power Plants 52.00
MW, Steam and Gas Power Plants 2,441.58 MW, and Diesel Power Plants 16,08 MW.
Total electricity sale for Jakarta Capital City Special Region in 2011 reached
35,061 GWh.
Energy Potentials
There is no primary energy potential
in Jakarta Capital City Special Region.
Electricity Demand Estimate
It is estimated that demand for electricity in Jakarta Capital City Special
Region in the period 2012-2031 shall grow averagely by 10.6% per year so that in
2031 electricity need shall reach 259.8 TWh. To fulfill peak utilization growth
of averagely around 10.4% per year until 2031, then additional power of
averagely around 2,181 MW per year shall be needed.