For those who are engaged in power plants development, I would like to share the following points with regard to the above subject. Warm regards.
Electricity Condition
Electricity
system of East Nusa Tenggara consists of some isolated systems
namely Kupang, Atambua, Ende, Ruteng, Bajawa, and Maumere systems. In 2011 peak
utilization reached 103.59 MW. Total installed capacity of power
plants in East Nusa Tenggara up to 2011 was 194.82 MW consisting of Diesel Power Plants 193.35 MW, Hydro Power Plants 0.12 MW, Mini Hydro Power
Plants 0.96 MW, Micro Hydro Power Plants 0.02
MW, and Solar Power Plants
0,37 MW. Total electricity sale for East Nusa
Tenggara in 2011 reached 487 GWh.
Energy Potentials
East Nusa
Tenggara has thermal and hydro primary energy potentials. Thermal
potentials are
estimated to reach 1,276 MWe in 19 locations namely Wai Sano, Ulumbu, Wai Pesi, Gou-Inelika, Mengeruda,
Mataloko, Komandaru, Ndetusoko, Sukoria, Jopu, Lesugolo, Oka-Ile Angie, Atadei,
Bukapiting, Roma-Ujelewung, Oyang Barang, Sirung (Isiabang-Kuriali), Adum, and Alor Timur. Hydro potentials are estimated to
reach 11.1 MW namely in Wai Ranjang.
Electricity Demand Estimate
It is projected that demand for electricity in East Nusa Tenggara for the period 2012-2031 shall grow averagely by 14.9%
per year so that in
2031 electricity need is expected to reach 8.1
TWh. To fulfill peak
utilization growth of averagely
14.6% per year until 2031, then additional power of averagely 110 MW per year shall be needed.